Church Repairs

Report of Churchwarden – Bill James

August 2018

The renovation project at The Church of Saint Mary and All Saints, Fotheringhay, continues apace, with all exterior work on the tower complete down to nave level and tower scaffolding, including all structural beams, removed to allow work on the nave roof itself to  progress.

Carpentry on the nave is now complete, with the lead ridge detail set to be finished by mid-August. Lead work to the rest of the nave roof is scheduled to be completed by the end of the month.

Carpentry and lead work to both aisles is complete and the installation of lead rainwater gutters and drainpipes has begun.

The majority of the masonry work is complete, with the exception of the East Gable which will not be completed until the scaffolding has been removed from that area.

Cleaning and decoration of windows is still to be agreed, subject to inspection and  approval of sample areas.

Given that there will be an intense level of activity related to the removal of scaffolding poles and the presence of contractors’ vehicles immediately in front of the main north doors, the Churchwardens have agreed a request that the church remains effectively closed to visitors during the working week, throughout the month of August.

The programme is progressing according to schedule.

Stonemasons’ Lament

The stonemasons at work on the church of Saint Mary and All Saints, Fotheringhay, might have been forgiven had they been heard to be humming the rather dubious and politically incorrect 1949 composition of Cole Porter entitled, “It’s Too Darn Hot!”  

Whilst the lyrics don’t bear close scrutiny, the sentiment seems right enough: it’s too hot to be doing anything.  In the cold Spring of this year, the stonemasons claimed to prefer warmer climes and restricted their mortaring to the more clement periods of dry and above four degrees. 

Now, in the Summer, it is the pervasive heat that is restricting their ability to make progress; it being so hot that the mortar dries too quickly, resulting in an unsatisfactory finish. 

To compensate, our stonemasons are arriving on site at 6:00am, ‘to get cracking’ early, before the mortar does the same!

July 2018
It is highly likely that access into our church will be restricted, with the site closed for periods of the working day during the whole of August to allow for the safe removal of scaffolding. Contractor’s vehicles will effectively block the main entrance into the building and the movement of equipment could pose a health and safety risk to visitors.
May 2018

Tower scaffolding coming down!

We are very excited to be able to report that all the high-level repair works to the weathervane and the major repairs to the timbers and lead of the tower roof have been completed.

Also, the very high-level stonework repairs to the tower have been done and as a result the scaffolding has started to come down from the tower.  The amount of work has been vastly more than we had expected, and costs currently are around £200,000 over budget.  The HB Allen Charitable Trust has very generously offered to cover a major part of these costs and the cost of restoring the weathervane has been paid for by a new £10,000 grant from the Masons together with the fundraising opportunity provided by an open day and the unique opportunity of visits to the top of the scaffolding offered to friends on Saturday 21st April which raised £2,100.

We are now confident that the tower is watertight probably for the first time in a hundred years or more! We can now admire the falcon and fetterlock weathervane in all its re-gilded glory!

 There are still some stonework repairs to the tower walls, repair work to the windows in the tower and the cleaning of the big west window to be completed before the scaffolding can be taken down to ground level but this is all likely to be done within a month or so.

Replacement of the leadwork and supporting oak on the south aisle is nearly finished and similar work on the north aisle is well advanced.

Inside the church, work in the north aisle is well on the way to completion and the removal of the interior scaffolding will start soon.

The east end of the church needs more in the way of stonework repair and repointing than we had expected, and this will cost a considerable amount more than we had been expecting but we do not have final figures yet.

 

Reconstructed Lead Gutters
 
Tower Roof Access
Regilded Fetterlock and Falcon
March 2018
A selection of recent photographs of the church repairs.  The church is currently wearing it’s Winter coat and looks rather camouflaged in the snow!  Note that the new servery is now installed.
January 2018
Please click on the link below to read our report on repairs to the Church roof.
September 2017 Progress

“Roof Scaffolding tops out on 25th September 2017″

It is with great pleasure that we are able to post this picture of the church with the tower fully scaffolded.

The nave and side aisles are still to be scaffolded but the temporary roof will go on the tower and work on the tower roof could start next week!”

 
August 2017 Progress Report
The major programme of building work has now commenced and our preferred contractors are on site. The church is now subject to health and safety regulations and access will be restricted and at the discretion of the site manager.
 IMG_0074  IMG_0076
For any enquiries or visits, please contact friendsoffc@btinternet.com